Material Acceptance on Site: Delivery Notes, Weighbridge Tickets and Acceptance or Rejection

Delivery discipline for concrete, aggregate and precast elements: checking delivery notes and weighbridge tickets, the sampling regime, acceptance and rejection limits, and the records to be kept on site.

30 August 202612 min read Ozan Global Holding
Material Acceptance on Site: Delivery Notes, Weighbridge Tickets and Acceptance or Rejection

The fate of the material entering a site is decided in the few minutes the lorry stands at the gate. If the delivery note is not read, the weighbridge ticket is not checked and the load is not looked at in those minutes, everything done afterwards is a correction. Material acceptance looks like paperwork, yet it bears directly on the life of the structure and the cost of the site. Set up properly, it does more than stop bad material; by recording which batch went where, it narrows the scope of any future problem to a single area. Below we set out the acceptance regime for concrete, aggregate and precast elements separately.

Why Is Material Acceptance a Process?

Acceptance is not a single signature but a four-step process: checking the documents, checking the quantity, inspecting by eye and, where needed, testing. Three of these steps are carried out while the vehicle is on site; the fourth is a record whose results arrive later. If the process runs in the same order for every load entering the site, you will have a dated, signed chain of records when a dispute arises.

Who carries out acceptance must be settled from the outset. Authority to take delivery of material on site rests with one person, usually the site manager or an inspector appointed by them in writing. If the person taking the paperwork from the driver is not the person accepting the load, nobody takes responsibility. On jobs subject to statutory building inspection, it should also be agreed in advance for which materials the inspector will attend in person.

The economics of acceptance are simple: the cost of turning a lorry away is negligible next to the cost of taking out and rebuilding work carried out with the wrong material. Even so, the sentence heard most often on site is “tip it and we will look at it later”. Once a load has been tipped, sending it back is practically impossible; from there on it is a negotiation.

There is also a time dimension. Acceptance records tie the material to the building element. Which wall was built with blocks from which batch; which floor was cast with concrete from which delivery? Without this information a doubt that emerges months later covers the whole structure; with it, the investigation stays confined to a single area.

Reading the Delivery Note: Common Fields and Product-Specific Fields

The fields that must appear on every delivery note are these: consignor and consignee details, date and time of issue, delivery address, type and quantity of product, and vehicle number plate. They may look like formalities, but they are the backbone of traceability. A delivery note showing another site as the delivery address tells you that the load is not yours; this happens more often on site than people suppose.

The ready-mix concrete delivery note is the richest of them all and carries additional fields: concrete strength class, consistency class, maximum aggregate size, exposure class, admixture details, quantity and the loading time at the plant. Every one of these is checked against the order. If the class or the consistency differs, call the plant before the truck is discharged; a difference in class waved through on site on a “close enough” basis leads to a far harder argument twenty-eight days later.

On an aggregate delivery note the product description is expected to be unambiguous: size fraction, whether the material has been washed, the intended use and the quarry details. A delivery note that says only “crushed stone” or “sand” gives you no way of proving which size fraction you received. Remember too that concrete aggregate and road material are declared against different standards; the description on the delivery note must point to the same product as the declaration in your hand.

On a precast element delivery note you will find the element type, dimensions, class, quantity and, where possible, the batch or production date. This information is checked against the marking on the element itself. The declaration of performance or certificate of conformity is also expected to arrive with the delivery; we covered documentation in detail in our article on conformity documents.

Writing on the delivery note is part of acceptance too. The time discharge finished, the measurement results on site and any note of objection are written on the copy of the delivery note that stays on site, and signed. If the driver’s copy leaves unsigned, that record is one-sided; the same note must be added to both copies.

The Weighbridge Ticket: Tare, Net Weight, Moisture and Tonnage Checks

For bulk materials the quantity is evidenced by the weighbridge ticket. The ticket must show the gross weight, the tare and the net weight separately; a ticket showing only the net weight cannot be verified. The weighing date and time and the vehicle number plate must match those on the delivery note. The validity of the ticket rests on the weighbridge having had its periodic verification; on large-volume purchases, asking for the date of the last verification is a reasonable request.

Where and when the tare is taken matters. The tare of the same vehicle changes with material or water left in the body. With a supplier you work with continuously, asking from time to time for an empty weighing of a randomly chosen vehicle confirms that the system is working properly. If a weighbridge cannot be installed on site, having periodic check weighings carried out at an independent weighbridge is another accepted method.

Moisture is the issue that loses most money on bulk aggregate. Sand loaded straight after rain, or straight after washing without being allowed to drain, carries a significant amount of water per tonne, and you pay for that water at the price of material. The same water also upsets the mix water calculation in concrete production. Keep a record when a load arrives wet; if it keeps happening, discuss stockholding and delivery arrangements with the supplier.

Another source of confusion is the conversion between tonnes and cubic metres. When the order is placed in cubic metres and the delivery made in tonnes, the conversion is based on the loose bulk density of the material, and that value varies with the type of material. The contract must state clearly which unit governs and how the conversion factor is to be established. Otherwise the same argument is repeated with every delivery.

Finally, stock control: compare the total tonnage entering the site with the quantity used in the works on a regular basis. If the difference is large, there is either a measurement error, a loss or a short delivery. Carried out weekly, this check reveals the problem while it is still small; carried out at the end of the month, its source cannot be traced.

Accepting Concrete: Time, Consistency, Temperature and Sampling

For fresh concrete, acceptance begins at the gate and continues until discharge is complete. The first thing to look at is the loading time. The time between leaving the plant and completing discharge directly determines the workability of the concrete; common practice is to require that this time does not exceed ninety minutes, and it shortens further in hot weather. If the time has been exceeded the mixer is not accepted; adding water on site to correct the consistency is not a solution but a new problem.

The second check is consistency. The slump test is quick and can be done on site. TS EN 206 defines consistency classes from S1 to S5; class S3, for example, corresponds to a slump range of 100-150 mm. If the class written on the delivery note does not agree with the measured value, repeat the measurement first, then call the plant. A slump higher than expected is usually a sign that water has been added on the road or on site, and it reduces strength directly.

The third check is the temperature of the fresh concrete. Common practice is to require that the concrete stays above five degrees and below thirty degrees; outside those limits, hot or cold weather concreting measures come into play. In a Bodrum summer the temperature measured at midday is often up against the upper limit; moving the pour to early morning or to the night is more effective than any measure taken afterwards.

The fourth step is sampling. A sample does not decide acceptance on the day, but it is the evidence of acceptance. It is taken from the middle of the discharge, labelled, and kept for the first twenty-four hours in the shade under a damp cover. We set out sampling, curing and reading the report step by step in our article on concrete sampling; what needs stressing here is that the acceptance record must show which mixer and which element the sample came from.

There is one more visual check: the homogeneity of the concrete. If you see segregation at discharge, if the coarse aggregate collects on one side, or if excess water gathers on the surface, there is a problem with the mix or with the transport. This observation is noted on the delivery note and reported to the plant the same day.

Accepting Aggregate: Visual Inspection and Simple Site Checks

Aggregate is largely accepted by eye and by hand; laboratory tests complete the picture but cannot be run on every load. The first thing to look at is cleanliness. If material that should have been washed arrives dusty, leaves a clear film of clay on the hand when squeezed, or keeps the water cloudy for a long time when rinsed, the fines content is high. Clay and fine dust prevent the cement paste bonding to the aggregate and reduce strength.

The second check is grading. If, looking at the stockpile, you see a distribution that does not match the declared size fraction — a large quantity of fine particles in material ordered as a coarse fraction, for example — the load has been mixed or the screening has not been done properly. Where there is doubt, a representative sample is taken and a sieve analysis carried out; on material bought continuously from the same supplier, this test is repeated periodically.

The third check is particle shape and soundness. Flaky and elongated particles reduce workability in concrete and create voids. Particles that break or crumble easily in the hand, or that look weathered on the surface, point to weak material. We explained the effect on concrete strength of the limestone crushed stone common along the Bodrum-Milas corridor in our article on aggregate quality; the criteria there apply at the acceptance stage as well.

The fourth check is foreign matter. If you can see lumps of soil, plant roots, pieces of timber, plastic or broken concrete in the stockpile, the material has been contaminated. We covered where recycled material can and cannot be used in our article on recycled aggregate; in a load ordered for structural concrete, pieces like these cannot be accepted.

On the laboratory side, results such as the methylene blue value, sand equivalent, Los Angeles abrasion resistance and freeze-thaw behaviour are read from the declaration of performance. These values are not measured on every load; but if the declaration contradicts what you see on site, taking a representative sample and having it tested is a natural part of acceptance. A representative sample is made up by taking material from several points and depths in the stockpile, not from one, and mixing it.

Accepting Precast Elements: Marking, Dimensions, Cracks and Gaskets

Acceptance of a precast element begins before it is lifted off the vehicle. First the marking is read: producer, product type and class, dimensions, production date and batch details. This information must match the delivery note and the declaration of performance. If it does not, the supplier is informed before the element is unloaded; a heavy element once unloaded usually cannot be reloaded.

Then comes visual inspection. There are only a few points to look at, but they matter: chipped corners and edges, voids and segregation marks on the surface, exposed reinforcement, deformed lifting hooks, and damage to the socket or spigot area. Fine shrinkage cracks on the surface must be distinguished from structural cracks; cracks that run from edge to edge, that are clearly wide and that follow the line of the reinforcement point to a transport or production fault and are not accepted without referring back to the producer.

The third step is dimensional checking. Not every element has to be measured; the critical dimensions of a few elements chosen at random from the delivery are checked — length, diameter or section, wall thickness and socket depth, for example. Erecting a precast system is sensitive to tolerance; a systematic deviation of a few millimetres accumulates along the line and turns into an erection problem at the end.

The fourth step covers the connection components. On gasketed concrete pipes, check that the elastomeric gaskets are of the right type, undamaged and present in sufficient number; remember that gaskets stiffen in the cold and must be kept at a suitable temperature before installation. In bolted, anchored or grouted systems the connection materials are part of the delivery too, and if they arrive short the erection stops.

Finally, unloading and stacking should be regarded as part of acceptance. The element must be lifted from the correct lifting points, the bearers must be placed as the producer instructs and the stacking ground must be even. A significant share of the precast damage met on site arises at this stage; the person carrying out acceptance should watch the unloading as well.

Acceptance, Conditional Acceptance and Rejection: Limits and Procedure

The acceptance decision ends in one of three ways. Acceptance is given when the documents, the quantity and the inspection results are all in order. Conditional acceptance is used when the non-conformity is limited and can be put right; for example, if a few elements have chipped edges those elements are set aside and the rest of the delivery is accepted, or a stockpile of aggregate is classified for use only in a particular part of the works. Rejection is given when the non-conformity concerns a fundamental property.

The situations that typically call for outright rejection are these: the concrete class on the delivery note differing from the order; the loading time exceeding the limit; the consistency clearly outside its class range; a grading in the aggregate that does not match the declared size fraction, or foreign matter in it; a structural crack or exposed reinforcement in a precast element; illegible marking; and the complete absence of a certificate of conformity. These items should be kept short enough to pin up on site and should be known to the whole team.

The rejection procedure must work quickly. The vehicle is not discharged. The situation is photographed; the number plate, the delivery note and the non-conformity itself must be visible in the photograph. A rejection note is written on both copies of the delivery note, the date and time are added, and the person accepting and the driver sign. The supplier is informed by telephone at the same time and then notified in writing. If the rejection is partial, the part taken is recorded together with its quantity.

The most critical point in a conditional acceptance is following the condition through. If the decision not to use the elements set aside stays on paper, those elements will go into the works a few days later. Material that has been set aside is physically marked, moved to a separate area where possible, and given a follow-up line on the acceptance form.

Where non-conformities recur, the decision has to be taken up to supply level. Wet aggregate, late mixers or damaged elements arriving one after another from the same supplier are not a site problem to be resolved case by case but a contractual matter. Acceptance records earn their keep here: you argue with dated records rather than with assertions.

The Record System: Who Writes What, and When?

The output of the acceptance process should be gathered on a single document. The material acceptance form runs to one page and contains the following lines: date and time, supplier, product and class, delivery note and weighbridge ticket numbers, vehicle number plate, quantity, the checks carried out and the measurement results, the codes of the samples taken, the acceptance, conditional acceptance or rejection decision, and the name and signature of the person accepting. One more line is added, and it is the most valuable of all: the building element the material will be used in.

The forms are filed daily and summarised weekly. The weekly summary compares the quantity received with the quantity used, lists the conditional acceptances still open and shows the test results outstanding. Without this summary the acceptance forms become an archive; with it they become a management tool.

No complicated system is needed on the digital side. With every load, the delivery note, the weighbridge ticket and, where there is one, a photograph of the non-conformity are taken on a phone, named with the date and the product, and dropped into a shared folder. Paper gets lost, gets wet and wears out on site; photographs survive. This two-minute habit answers a question asked months later.

The second function of records is learning. Looking back over the acceptance records at the end of a period shows which problem recurs with which supplier, which non-conformity increases in which season, and which check genuinely earns its keep. If the supply plan for the next project is built on this data, the acceptance process stops being a cost item and becomes a way of saving money.

One final reminder: acceptance discipline is also a measure of the relationship you build with your supplier. Working with a supplier who discusses the delivery programme, the flow of documents and the sampling protocol from the outset noticeably reduces the workload on site. Along the Bodrum-Milas corridor, Bodrum Beton runs delivery and quality records for ready-mix concrete, İTS Maden handles size fraction and declaration details for aggregate and sub-base material, and Bodrum Boru manages marking and document flow for concrete pipes and precast elements, in each case working alongside the site. To draw up the material acceptance protocol for your project, you can reach us through the contact page.

Frequently Asked Questions

How long can a ready-mix concrete truck wait?
Common practice is to require that the time between loading at the plant and completing discharge does not exceed ninety minutes; in hot weather it shortens further. If the time has been exceeded the mixer is not accepted. Adding water on site to correct the consistency is not a solution and reduces strength directly.
What should I look at on a weighbridge ticket?
Check that the gross, tare and net weights are shown separately, that the weighing date and time are given, and that the number plate matches the delivery note. A ticket showing only the net weight cannot be verified. On large purchases it is reasonable to ask about the periodic verification status of the weighbridge and, from time to time, to request an empty weighing of a randomly chosen vehicle.
How can I tell on site that aggregate contains too many fines?
Take some of the material in your hand and squeeze it; if it leaves a clear film of clay, the fines content is high. If you put it in a container of water, shake it and the water stays cloudy for a long time, you reach the same conclusion. Where there is doubt, a representative sample is taken and a sieve analysis and the relevant tests are carried out.
Is every crack in a precast element grounds for rejection?
No. Fine shrinkage cracks on the surface are generally acceptable. Cracks that run from edge to edge, that are clearly wide, that follow the line of the reinforcement or that form around the lifting points are treated as structural signs and are not accepted without referring back to the producer.
What should I do when I reject a load?
Do not let the vehicle discharge. Photograph the number plate, the delivery note and the non-conformity itself; write the rejection note with the date and time on both copies of the delivery note and have it signed by the person taking delivery and by the driver. Inform the supplier by telephone at the same time, then follow up in writing.
How detailed should material acceptance records be?
A single-page form is enough: date and time, supplier, product and class, delivery note and weighbridge ticket numbers, number plate, quantity, the checks carried out, sample codes, decision and signature. The most valuable line is the building element the material was used in; that line narrows the scope of any future investigation to a single area.